Saturday, 14 January 2017

The bunker project- Finishing touches



Carrying on from my previous blog I thought I would tell you about the last stages of the project. I also have a you tube video you can watch to get you in the mood for the new bunkers. 
Here is the link below:-

After a delay of nearly a month on the Heather turf due to unseasonal dry weather and issues with the companies lifting equipment. It's worth remembering last year we were a trial site and it was lifted by hand. This year they have orders from a few very big clubs also, so they needed to make a machine to lift big areas quickly, making it easier for the guys to lay our end. So this took time too. 



The Heather turf arrived at the beginning of December... 52 pallets to be precise. Meaning we had a very busy run up to Christmas. 



The look we got from adding the Heather turf is something pretty special. It's aged the bunkers making them look like they have been here forever. Graham and myself, went to see the Heather turf being lifted and also collect pictures of what natural Heather areas looked like so we could replicate this back at the club. 



After a team briefing showing the greenstaff our pictures on the big screen the guys really understood what we wanted and done a great job. 


The surrounds and swails with the added Heather look natural and it really frames the hole. I have also been impressed with the quality of the Heather turf. Let's hope we get some rain to help bed it in! (Over night only would be perfect ;-)


With all 52 pallets of Heather turf out before Christmas the team got a much needed rest. 
They have had such a busy season and we have spent over 2200 man hours on projects alone. That works out as one member of the team working 42 hour weeks every week for a year just on projects! Obviously it doesn't happen like that as we have other things like running the golf course and competitions but you get my drift. 


So much work has been done on the course that I have been asked to go around the country in various places and to talk about 'Stoneham' to Greenkeepers, trade and General Managers. All this is great PR for the club and others are looking at what we are doing.
Okay, I m going off on a tangent now. Back to the bunkers. 

Now into January and the weather is still dry enough for us to get some sand into the bunkers. 



This isn't the final levels but the first layer. PLEASE DO NOT PLAY FROM THE BUNKERS. 
The Heather turf and turf haven't rooted well enough yet to take sand splash. 

The sand in the bunkers will get chance to settle and compact down and we will top up until the levels are right. The bunkers will open as soon as they are ready but not before. 


We also added Heather Turf to the 1st tee. Replacing the old hedge with heather has enhanced the view from the clubhouse and pro shop area and the Heather has brought the feeling of the golf course to the first tee. 

Following this we will cut in the last areas of heather, tidy and top up the drain lines ahead of the season. 

Other work's have included cutting, flymoing and preparing the new turf areas, woodland management, placing out winter mats on the high wear tees. Spraying the greens to try and prevent disease and add wetting agents. Edging bunkers and weeding and general works to get the course tidy following all the works. 


With the winter solstice done and now in mid January the season will soon be on us. 

We just have February traditionally the coldest month of the year to go and then (let's hope) boom! 


I hope you agree the new bunkers are starting to look the part and they have both improved the course strategically and aesthetically.  

Matt 



Monday, 9 January 2017

The bunker project- Coming up to the finishing line


We have so much going on at the club at the moment from clearing leaves to project work I am finding it hard to keep up the blogs, not a bad thing as its great to see so much work going on. 


In my last bunker project blog 'The Welsh Wizard' we spoke about the works being done by Nathan and Nick to get the bunkers shaped from subsoil to the drainage, to the base and then the bunker blinder liner. 

Now I am going to talk about the next stage of the build. 

The revet turf 


Once the blinder base was added we started the revetted edge to the bunkers. This was built on the shelf created during shaping that is also blinded so we can always find the edge and repair in the future years the to exactly the same place. 

The revetting turf comes in slabs approx 35mm thick. Each slab measures 1.2m by 0.6m. The slabs were cut in half lengthways to produce strips measuring 1.2m by 0.3m. The revet is laid like a wall with no joins in the same place and yes greenside up! 

At this point we had looked at 'how' we were going to do the revetment here at Stoneham. Murray Long suggested we changed from the traditional way of just a plain 3 revetted turf edge and add some movement like our old traditional bunkers we have already. This would give the appearance that some of the Heather the turf once in would be rolling over like the Willie Park bunkers we have already. 
We also knew we would need to add height to certain banks by adding an extra layer to. 


Before 

After 



The greenstaff did a great job on the revetment and the back filling behind it.




Top soiling 
Once all the revetted edges were complete we then moved on to the top soiling. These were the stock piles you would have seen next to the bunkers that everybody thought were new huge mounds! 



Nathan (the shaper) then distributed the piles out around the bunker at a depth of 4-6 inches (depending on slope). If the area didn't have enough top soil, then we added a rootzone that we purchased. This was shaped in by Nathan and then healed in and raked again and again (please see picture at top of blog). At this point we said goodbye to Nathan and Nick as they moved on to shape another course. They done a fantastic job for us and I think everyone could see the skill that Nathan has with his digger. 
It was sad seeing them go but we know they will be back before we know it to carry on with this amazing project. 





Turfing 
Once the topsoil was all in place the turfing began. There was a mix of turfs out on the course depending on location.



 A dwarf rye mix was used around the green side bunkers and swails to match the existing turf. This can be cut tight and is hard wearing which is perfect for these areas. 



The fairway bunkers were turfed with pure fescue because they will be mixed with Heather. This can then be left long, giving a whispy natural look. 



You may have noticed that some areas were left bare, once the turfing was completed. These areas were left for the heather turfing. 

The turf was laid in the traditional way with over hand left in the bunkers. These were cut off using a saw (it gives a better finish) and blended in to the revetted turf. 

All the turfing was completed in 5 days. That's over 4000m2 of turf down in an incredibly quick period. 

Drainage outlets 

With the turfing complete, Profusion left us to complete the final stages. 



Next on the list was the drainage outlets. We had on site the trencher I borrowed from Muswell Hill GC, which allowed us to complete the drainage. We used 80mm perforated pipe running to a positive outfall (either a ditch or low area) as close as we could find to the bunker. Some of the runs had to go 200-300m 13th green to 5th ditch for example to get a good drainage run. 


Only two bunkers on the 5th and two bunkers on the 1st and 3rd could be drained to a soak away. 
The ones on the 1st and 3rd are over gravel so they should be perfect. We will monitor the 5th to see if we need to drain from the soak away to a ditch but heights and falls were making this a big project and we had enough fall towards the woods so a soak away option is being trialled here. 



Our other big issue during this stage was irrigation. 
The irrigation system was laid in the ground at different stages and in different places to the plans. This caused us a huge problem. Areas were cat scanned and cables 
marked. 

Normally the cables are laid at the same time as the pipe work as above. This is done so the pipe work can always be traced for future works. The trouble we have is the mains went in first and then the cable some years later. Meaning we can't find the pipe work!! Even the plans for where they wanted to lay them are not close and the depths of installation are all different making it impossible to miss. 
So obviously we found the pipe work and cable with our trencher! 
This meant 13 repairs to the system, just adding outlets to the bunkers. These all had to be dug out, repaired, and left open until all the repairs were completed before we could test them and back fill them. Huge man hours were used on this along with our irrigation engineer just to get it sorted. 

It just goes to show you, you can never plan for everything and you are always learning. Next year I have now planned time and a budget should this happen again (it will I fear) but this is something we will work on in the future when we have to upgrade the system. 

Okay, that's enough from me. I will blog again about the finishing touches of Heather and Sand. 

See you all soon 

Matt 





Saturday, 24 December 2016

Merry Christmas and A Happy New Year



Just a quick blog to wish you all a Merry Christmas and a Happy New Year 
Hope you have a fun filled few days with the loved ones and maybe even the odd round of golf! 

The team have worked very hard this year and will be getting a well deserved break but don't worry we will still be out on the course daily to set up. 

Thank you for all your support this year. 

Happy holidays 

Matt and the Greestaff 

Sunday, 20 November 2016

It's snowing leaves


I just wanted to write a quick blog about the clearing and tidying up of the leaves!

This is a non stop task for the team from October until the new year. 
Last year we spent over 900 man hours clearing leaves from the course. 
This year we have an even bigger challenge. Not only have all the trees on the course got bigger (remember the trees are constantly growing year on year) but due to the mild wet winter last year we have an even bigger amount of leaves on the trees. Why? Because the mild winter meant the trees metabolism never slowed down add to this the extra sunshine of 2016 meaning the tree was able to photosynthesis more. Speaking to different arboriculturists this year I was told they had really noticed and the difference is huge! 
 
I have mentioned this before but the average Oak tree has 300,000 leaves, we have hundreds and hundreds of Oaks on the course and this is a 'bumper year' for leaves so imagine how many we need to remove... Answers on postcard please! 

Autumnal colours visible on the course


Okay, that's enough of the amazing colours, let's talk about what we are doing:-

We have added new machinery to our existing leaf clearing fleet over the last 12 months. These include- 3x back pack blowers, 1x Pro force blower (like jet engines), 1x big tractor mounted blowers, 1x  SG400 Trilo vacuum
The new Grillo cut and collect system (above:- used for Heather and long roughs) also can be used as a small vacuum system. 




Our aim everyday now is to clear the main playing surfaces by hand (note picture above shows we are now hand mowing greens too). 


These are then blown into lines or back into play (sounds mad I know) but these can then be vacuumed up! 

Once vacuumed up the leaves are taken to various sites around the course to be composted. 



Once we have cleared the main playing surfaces our attention will turn to the ditches, woodlands and Heather areas. These all need to be cleared for different reasons, firstly the ditches are needed to dry the course out in the depths of winter. 


Secondly leaf mulch will suppress some of amazing flora and forna we have during the season in our woodlands and Heather areas. Getting leaves out of Heather is a very time consuming effort but is worth it. 


The high winds of late and the frosty mornings are just what we need to get the leaves down and down quickly is how we prefer it because we can then get a good clean up completed. 

So please bare with us in the coming few weeks why we do our best to stay on top of this huge task, it only takes one gust of wind to undo hours of work. The team are working hard to clear the leaves for you! 

That's enough from me... We have leaves to collect.

See you soon 

Matt 




Monday, 24 October 2016

13th Green Drainage


As I sit here to write this blog I must admit to feeling slightly relieved that we have finished this project.

For all greenkeepers pitchmarks and scuffs on the green are a major headache, so you can imagine how it must feel to see the sacred turf lifted and soils below removed! 
This kind of project is not taken lightly but needs must. 


Last winter I got to see first hand, how wet the 13th green got. The moisture readings were around 57% in the winter, this is 27% higher than we want. (Moisture levels over 50% basically means the grass starts to die off as there is a lack of oxygen to sustain itself). 



Is drainage the right decision? 

After the readings we had last winter and the extra aeration and the days the green was kept out of play I knew we had no option but to drain the green. I needed more evidence to back up the theory. So we had soil analysis of the greens done. 

The results showed the top 4 inches are very sandy but below this a high amount of clay was present. This showed that infiltration rates would have been high but percolation rates would have slowed to practically nothing. In others words more water coming in from the top than realising out of the bottom. Like covering over a plug hole with a sponge and running a tap! 
This was all the evidence we needed and the plan was made. 

Timing!

Now we knew for certain that the green required drainage, we planned the work to coincide with works around the green with the bunker project. This would work perfectly as the bunker and surrounds would require drainage too. This meant we could plug the green into that to save re doing it in the future. 

The job itself 

Okay I've given you all the information, I need to just talk about how we drained the green...! 


First we laser levelled the green to find which was the best place to put the drainage runs. 
(At this stage we were surprised the green moved a different way from the way it actually looks by eye, with a 50mm from right to left and front to back). 

We then marked the main and added the laterals in at 3m centres. The reason this is closer than fairway drainage is the speed we want the green to drain at. (Obviously we want the entire course to drain better but all drainage costs money but our priority has to be draining the greens the quickest so play can continue). 
The general rule is greens,tees and aprons 3m spacings, fairways 5m, roughs and semi rough 10m. 


Next the turf was cut and lifted. As we lifted each section it was numbered and placed on a tarpaulin (to stop it rooting, while off the green). The end of each line was numbered + letter (M= Main L= lateral) so the turf would go back exactly where it came. This over time would mean the world would be seemless.


During this process we found the middle of the green was showing signs of anaerobic conditions (suffocation, even before the winter had set in). This can be seen in the picture below. The soil is turning black. You can see where our aeration work has been done because this is sand coloured.

At this point I knew we were doing the right thing. This green wouldn't have survived the winter. 


Once the turf was stripped we were ready start the drainage. 

The green was trenched out and the spoil was used towards shaping the sub base of the new bunker on 13th. So keeping the runs short and the trencher going. 

This is the trencher we borrowed from Muswell Hill GC (thanks to the them). 

Lots of digging out at the ends to get the levels right was required and the greenstaff done a great job on it. 
You can also see the width of the turf cut and the trenched line leaves very little in the way of room! Both Graham and I had "fun" with this but we managed it.

Our main was trenched to 650mm and our laterals were 600-550mm deep. The bases were lasered and the levels corrected before and stone or pipe was added. 

Drainage needs to be deep for two reasons. One so aeration avoids it in the coming years or there will no point putting it in as this will be a pipe with hundreds of holes in it and secondly to encourage a 'pull' so the water heads to the pipes, this creates a vacuum in the soil and pipe work, making the drainage work efficiently. 

At this point we could see the underlying problem in the middle of the green. A clay layer just 120mm down. This grey clay is our problem. Our infiltration rate would be high as you can see the sandy/soil layer above but once it his the grey clay it would go nowhere. 

This green would have be built like this on purpose... 

The reason would have been irrigation! 
I know it's mad when I am talking about drainage but old greens (before the 1970's) were built with a clay base to hold water as irrigation systems didn't exist in the summer so they wanted them to hold water. Irrigation system started as a hose pipe but later computer controlled were not really popular until the early 70's. 
Golf has changed and greens that were built to hold water and now required to drain and play well in the winter, hence why these works and maintenance weeks works are essential! 

Once the levels were right a stone base (1/2 inch) was added for the pipe to sit on. I like to do this to keep the pipe as clear from silts as possible. 

Next the pipe work was added. The laterals were 60mm (self flushing)
And the mains 80mm. 


The mains was then linked up with the bunker project and runs to a ditch. This means at each stage the outlets get bigger from the start!


At this point it's worth noting on the greens all work too place in boards. These needed to moved and the area cleaned constantly so damage to the greens surface was kept to an absolute minimum. Again the team done a great job at this stage too.


Once the pipe was in and the joins made we then added the stone layer. We used our new conveyer system on our topdresser. This saved a lot of manual handling and increased our speed. 

After the stone the rootzone was added in layers and then compacted in. This is very labour intensive but helps to minimise sinkage in the future. 
The rootzone was made from the same sand as the club has top dressed with for years so it was compatible. 

Once our levels were high enough we used a modified wacker plate to compact the top layers. This saved time and done a great job. Thanks to Parkstone GC for lending us that too. 

During the whole project we had to keep the rest of the green in good state for re opening. This was mown by Levi using a hand mower three times a week. It definitely tested his skills!! 

During the final 3 inches of topping up we added mycorrhizal fertiliser to the soil to encourage rooting ASAP once turfed. The final level was then finished using a normal wacker plate. 

The green was then turfed using the turfs in the same places like a numbered jigsaw.  Great care and attention were needed at this process too as our mowers cut at 3 to 4mm so the levels have to be spot on. 

The green was then fully turfed and just needed time to recover. 

The aftercare

Four days after turfing the green was rolled for the first time to smooth it out. I was already impressed with the rooting at this stage. This is something we have carried on with.

The drain lines were topdressed before opening and again this is something we will work on to get the final levels right. 

The following Friday after we turfed the green was looking a lot better. Little and often liquid feeds will be on going now. 

7 days after we laid our last turf the green opened back up for play. The speed of the recovery and rooting was brilliant. 

My final thoughts 

For me the green basically got heart surgery and this should make a huge difference as we go forward. 
The greenstaff done a fantastic job from start to finish and I couldn't have asked for more. Thank you guys! (Thanks also to Richard and Jayne and the pro shop for keeping the membership and visitors informed of our work).

All the work was completed in 22 days start to finish (not bad considering it was out of play for over 30 days last year due to water logging). 

We still will be working very hard on this green in the coming months but it will now drain and the future for that green is very bright or dry :-) ! 

PS

While I am talking about drainage, it was nice to see Graham got some pictures in our recent down pour from the 17th, you can see the drains doing there job! 




I hope this has helped to show you the works that have been going on. Sorry it's a bit later than normal. Finding time to write all this down is hard! 

Next blog... The bunkers stage 2

Matt